SAM'S SENSE: Miracle stadiums, in darkness
Audio By Vocalize
Recently President William Ruto was in the North Eastern region. Among
many other things, he was there to commission the construction of Wajir
Stadium, at a cost of Ksh.900 million. The facility, the President said, should
be ready in under four months, ready to host the Madaraka Day celebrations, the
first of such in the region. Park that for a moment.
Let me tell you a story of the quest for stadiums. Kenyans love them.
Even the ones they don’t have, they aspire to have. In the villages it is not
unusual to find a dusty beaten patch being nicknamed Old Trafford. Or a sandy
open grassland teeming with thorns and cactus being christened the Emirates, no
pun intended. All because, Kenyans love good sporting facilities.
The election promise to build five stadiums by the so-called dynamic duo
of Uhuru Kenyatta and William Ruto in 2013 excited a significant chunk of
Kenyans. It was a promising, even thrilling list. They said they would, and I
quote, “build five new national sports stadia in Kisumu, Mombasa, Nakuru,
Eldoret and Garissa, while upgrading existing sporting facilities at the county
level to accommodate swimming, tennis, basketball and rugby.” End of quote, and
promise.
As Deputy President, William Ruto in 2017 improved the promise from five
to nine stadiums, replete with timelines ranging from three to six months. But
that is water under the stadium, rather, the bridge.
Talanta Stadium is up and on course and based on images shared, may well
meet the expectations of many Kenyans. We will talk about the cost of Talanta
some other day. Another day because there is a worrying dark side to the clear
endeavors to construct stadiums around the country.
I begin this illustration in Kericho, the green stadium that hosted
Mashujaa Day in 2023. It is now known as Kiprugut Chumo Stadium. The Auditor General
reports that the refurbishment of that stadium cost Ksh.408 million. It started
with a letter from the Internal Security Principal Secretary on July 19, 2023
to the Sports PS informing that the Mashujaa Day of that year would be hosted
at the Kericho Green Stadium. The Director General of Sports Kenya had informed
the Kericho Governor of the same on a day before. And refurbishment works were
to commence.
But then, according to the auditor, the contract was awarded on September
4, 2023. By which time there had been engagements between the contractor and
the procuring entity – Sports Kenya - as early as July 19, the day the PSs
exchanged notes.
A day after the contract was signed, meaning the 5th of September, it
was communicated that the contractor had achieved 50 per cent progress in the
works, and therefore a part payment of Ksh.183.6 million was due.
The auditor noted that the works must have begun way before a contract
was awarded. The auditor established that the contractor had issued a letter of
acceptance on the 14th of August 2023, nearly three weeks before he was awarded
the contract. Let that sink. You accept a job, before one has been offered, and
you sign papers to confirm that.
There’s something more. The auditor found that the said contractor only
registered with the regulator, the National Construction Authority on the 29th
of July, ten days after the contractor had interacted with Sports Kenya and
even submitted designs for Kericho Green Stadium. I know, the dates are already
confusing.
It is simple. The construction of Kericho Green Stadium must have been a
boardroom deal that was inconvenienced by the bureaucracy of procurement. The
auditor stated that the management was in breach of the law and that the
regularity of the expenditure could not be confirmed.
Away from the green. The President has made a new promise, in the North.
Wajir must have a new stadium for the 1st June Madaraka Day celebrations this
year. That is in three months’ time. Unless you are a miracle architect, how
can you put up long-lasting sporting infrastructure in three months?
And what is the rationale here? Are we proposing, adopting, contracting
and implementing stadiums purely for national holidays?
Also, when the Kenya Defence Forces and the parent ministry are
instructed to make it happen, at a cost of Ksh.900 million, how was the
procurement process done?
Are we using the KDF to put up sporting infrastructure away from the
sports departments to escape the rigorous accountability demands?
The President also promised another stadium in Mandera at a similar cost
of Ksh.900million, which must be ready for the locals to celebrate Jamhuri day
there, this December.
As we speak, the Kericho stadium running track is chipping.
Infrastructure there is not up to standard. The Ithookwe stadium in Kitui that
hosted Mashujaa Day last year after a marathon four-month construction is not
yet complete - four months after the event. It’s been deserted. Why the rush in
the first place? Where’s the value for money?
And as we build these essential pieces of sporting infrastructure,
thousands of residents in host counties are starving or facing starvation as
their livelihoods risk extinction by the harsh climatic conditions. For now,
let us play, or pray, IN THREE MONTHS’ TIME.


Leave a Comment