Lake Turkana Wind Power scam: Auditor General wants ex-KPLC boss Njoroge, ex-PS Nyoike probed
The Auditor General wants those who were in
charge of the Lake Turkana Wind Power project investigated and those found
culpable punished.
The power purchasing agreement between Kenya
Power and Lake Turkana Wind Power Limited that saw Kenya incur Ksh.18 billion in
penalties for power not used was executed during the reign of the then KPLC
Managing Director Engineer Joseph Njoroge and then Energy Permanent Secretary
Patrick Nyoike.
This as it emerges that Kenya Power and the
Ministry of Energy mandarins ignored warnings from the World Bank.
The government of Kenya had reached out to
World Bank to indemnify the project but upon assessing the power purchasing
agreement and the scope of the project, the World Bank opted out.
The Auditor General’s report indicates that
World Bank warned the large size of the wind power plant could have had an
impact on the reliability of systems supply.
With the wind power project expected to
produce 300 megawatts of power, World Bank advised Kenya to develop its wind
power project gradually in smaller lots of between 50-100 megawatts.
The World Bank also warned against the single
sourcing of Lake Turkana Wind Power Limited to carry out the project.
The company initiated the project in 2006
through a project proposal to Kenya Power.
The power utility firm jumped onto the
proposal in 2009 with the board ratifying the decision to directly engage Lake
Turkana Wind Power Limited without going through the procurement process.
What followed was a dash to approve a
decision to have Kenya Power enter into a power purchasing agreement with Lake
Turkana Wind Power Limited. Within a record time of one week, KPLC had obtained
the green light.
The World Bank was equally skeptical of the
pay deal entered in the contract warning that it exposed KPLC to unacceptable
high financial risk.
The delay in the construction of transmission
lines from Loiyangalani to Suswa that resulted into the Ksh.18 billion penalty
had equally been foreseen.
The World Bank quipped the 26-month period as
envisaged was too short to realize and that finally Kenya Power lacked the
experience in managing dispatch from a large wind power installation into its
power system.
Either by design or default, all these red
flags were ignored.
The Auditor General now wants a further probe
to be carried out to ascertain if there were any acts of omission or commission
on the individuals involved in the entire set up of the project and any
culpability punished.
The special audit report also wants the Energy
ministry and KPLC to be held accountable for not ensuring a competitive process
in identifying and implementing the project to ensure fairness, transparency,
equity and cost-effectiveness and not conducting an independent legal risk
assessment prior to executing of the wind power contract.
Out of the Ksh.18 billion penalty accrued
from the delayed evacuation of ready power from Loiyangalani due to the 21
months delay in completion of transmission lines to Suswa, the Ministry of Energy
has paid Ksh.10 billion.
The audit report has warned that the balance
of Ksh.9 billion will be passed on to consumers by KPLC until the year 2024.
Want to send us a story? SMS to 25170 or WhatsApp 0743570000 or Submit on Citizen Digital or email wananchi@royalmedia.co.ke
Comments
No comments yet.
Leave a Comment